Coerco: Supporting Tower Hill Pit Dewatering with Advanced Solutions

Floating Pontoons, Pipefloat

 Coerco Supports Tower Hill Pit Dewatering for Greenlands Equipment

Greenland-4

Download Case Study


The Challenge: Dewatering Tower Hill Pit

Genesis Minerals faced the critical challenge of dewatering Tower Hill Pit in Western Australia to safely commence mining operations. This required a high-capacity pump system capable of delivering water at 80L/s while integrating seamlessly with the site’s SCADA telemetry system and incorporating a robust leak detection mechanism to ensure operational safety.

Greenlands Equipment’s Turnkey Solution

Greenlands Equipment delivered the complete turnkey solution for this project, which included:

  • Design and Engineering: Developing a comprehensive dewatering system tailored to the site’s requirements.
  • Equipment Manufacture: Ensuring all components met the rigorous demands of mining environments.
  • Installation and Commissioning: Overseeing the on-site setup and integration of the pump system, pipework, and leak detection system.

Coerco’s Key Contributions

Coerco played a vital role in supporting Greenlands Equipment’s execution of the project by supplying precision-engineered products that met the project’s high-performance standards.

PNT-P-600 Bore Pump Pontoon

Coerco’s PNT-P-600 Bore Pump Pontoon provided the foundation for the dewatering pump system, delivering:

  • Durability and Stability: Engineered to support the pump system reliably, even in harsh mining environments.
  • Corrosion Resistance: Built with heavy-duty polyethylene to withstand prolonged exposure to challenging conditions.
  • Seamless Integration: Designed to accommodate the pump system with precision, ensuring optimal functionality.

Learn more about Coerco Pontoons here

MTF130 & MTF75 Pipe Floats

Coerco’s Pipe Floats were instrumental in protecting and supporting the HDPE pipework integral to the dewatering infrastructure:

  • Superior Buoyancy: Maintained stable and efficient water transport throughout the operation.
  • Robust Construction: Manufactured from high-density polyethylene for impact resistance and long-term durability.
  • Versatile Application: Provided reliable support and protection in the dynamic conditions of a mining environment.

Learn more about Coerco Hose and Cable Floats here

 

The Results 

Enhanced Durability and Safety

Coerco’s high-quality components ensured the dewatering system could withstand the operational demands and abrasive conditions of the site.

  • Improved Safety: Leak detection and secure pipework mitigated potential risks.
  • Long-Term Performance: Corrosion-resistant materials and precision engineering offered enduring reliability.

Efficient Collaboration and Delivery

While Greenlands Equipment managed the project’s implementation, Coerco ensured seamless delivery of its products to their Perth facility:

  • Reliable Logistics: Coordinated deliveries met project timelines and specifications.
  • Collaborative Support: Worked closely with Greenlands Equipment to ensure all components were ready for integration.

 

greenland-image-1

 

Partnering for Excellence

At Coerco, we believe that great outcomes stem from collaboration and innovation. For the Tower Hill Pit dewatering project, we partnered with Greenlands Equipment to deliver tailored solutions that met the project’s complex demands. From our advanced PNT-P-600 Bore Pump Pontoon to our state-of-the-art pipe floats, every component was engineered with precision to perform in the toughest conditions.

This project is a testament to Coerco’s dynamic and reliable approach, backed by years of experience and a commitment to delivering exceptional results. By working closely with Greenlands Equipment, we helped ensure that this critical mining project was completed safely, efficiently, and on schedule.

 